The Payment Mechanism

In an earlier post we examined Late Payment and the remedies that are available when a Payment is made after the Final Date upon which it was due to be paid.

In some contracts this is straight forward as it can be clearly stated, such as 14 days from the date of invoice etc.

Construction Contracts and indeed any contract that made regular payments based on progress made or value earned and applied for through an Interim Application for Payment (AfP) can be more complex as they need to be in accordance with a number of documents in ensuring the Payment Mechanism is in accordance with current legislation, regulation and statutory instrument. Further where a standard form of contract is used, the terms and conditions in this contract need to be considered, to ensure they are not in conflict with the Acts and Statutory Instruments.

You can at times end up having tyo ensure that you are in accordance with the requirements of 5 separate Documents. These being:

  • The Housing Grants, Construction and Regeneration Act [1996]
  • Local Democracy, Economic Development and Construction Act [2009]
  • The Scheme for Construction Contracts (England and Wales) [1998]
  • The Scheme for Construction Contracts (Amendment) (England) [2011]
  • The contract that is going to be used e.g. Joint Contract Tribunal (JCT), New Engineering Contract (NEC)

In Scotland both The Housing Grants, Construction and Regeneration Act [1996] and Local Democracy, Economic Development and Construction Act [2009] applied. However Scotland had their own Statutory Instrument, The Scheme for Construction Contracts (Scotland) [1998]. Initially the proposed amendments  were laid before the Scottish Parliament for approval. However the amendments subsequently become law through the 2011 amendments coming into force as a United Kingdom Statutory Instrument. The draft regulation in relation to Scotland can be viewed at this link,  http://www.legislation.gov.uk/sdsi/2011/9780111014431/pdfs/sdsi_9780111014431_en.pdf

As can therefore be seen ensuring a Payment Mechanism is legal and workable can be something of a minefield, particularly when the contracts begins to run late invoking Liquidated & Ascertained Damages (LAD’s) or Extension of Time (EoT).

Next time we will examine the Payment Certificate and Payless Notice.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s